5.1. Preparing the Board for the Board Test System
With the power to the board off, follow these steps:
- Plug the included USB cable from J37 ( Intel® FPGA Download Cable II interface) to the host computer's USB port.
- Ensure that the development board switches and jumpers are set to the default positions as shown in the Factory Default Switch and Jumper Settings section.
For more information about the board’s DIP switch and jumper settings, refer to the Cyclone® V SoC Development Board Reference Manual .
CAUTION:
To ensure operating stability, keep the USB cable connected and the board powered on when running the demonstration application. The application cannot run correctly unless the USB cable is attached and the board is on.