AN 1006: Multi-Project Analysis with Exploration Dashboard
ID
816589
Date
11/18/2024
Public
A newer version of this document is available. Customers should click here to go to the newest version.
2.1. Step 1: Create an Exploration Dashboard Workspace
2.2. Step 2: Add Projects to Exploration Dashboard
2.3. Step 3: Launch Connections and Compile the Projects
2.4. Step 4: Import and Analyze Timing Summary Reports
2.5. Step 5: Analyze the Results of Report Timing
2.6. Step 6: Disconnecting Interactive Connections
2.6. Step 6: Disconnecting Interactive Connections
When you are done with analysis, you can disconnect the interactive connections by following these steps:
- On the Tasks list, click Disconnect Interactive Connection. The Disconnect Interactive Connection dialog box appears.
Figure 25. Disconnect Interactive Connection Task
- Turn on Clean up revisions before disconnecting to instruct Exploration Dashboard to delete each revision itself, instead of simply closing. This option manages the impact on disk usage once your work is complete.
Figure 26. Disconnect Interactive Connection Dialog Box Options
- To close the interactive connections in the workspace, click OK.
Note: When you close Exploration Dashboard, all imported data is automatically saved and persists in the workspace. The data reappears the next time you open the workspace, so there is no need to save the workspace independently.